Oracle sent a force majeure notice over its OpenAI-linked New Mexico data center

Oracle sent a force majeure notice to a Blue Owl unit developing the 1,400-acre Project Jupiter campus in Doña Ana County, citing delays in securing power.

Story date On the site Updated: Türkçe

CorrectedThis story was corrected after publication (Oct. 9, 2026). Details

3 sourcesJump to sources

Sources: Bloomberg, Reuters, Source NM

In this story
  1. Sources3
  2. Corrections and updates1
  3. About this story
  4. Related1

The notice went to a Blue Owl unit developing the 1,400-acre Project Jupiter campus in Doña Ana County, citing delays in securing power. It would let the company defer payments should the site miss its 2028 target. The campus is part of Oracle’s agreement to supply capacity to OpenAI and of Stargate. A natural gas pipeline meant to start service in mid-August and fuel the site was pushed back nearly six months to February 1, 2027. Oracle shares fell on the news.

Sources

3 sources

Corrections and updates

1 note
  1. Correction

    The version first posted on Instagram said the gas pipeline was due to start service “this month.” According to Source NM, citing FERC filings, the original in-service date was August 15, 2026; the text has been corrected.

About this story

Written by
· JARRUS
Story date
On the site
since Sept. 27, 2026
Instagram
@jarrus.tech posted this story on Sept. 27, 2026.
Report an error
Spotted an error in this story? [email protected] · Instagram

Related

  1. 2 sources

    Oracle’s $18 billion data center loan fell to 89-⁠91 cents on the dollar