Oracle sent a force majeure notice over its OpenAI-linked New Mexico data center

Published: Updated: 3 sourcesTürkçe

This story was corrected after publication (Oct. 9, 2026). Details

The notice went to a Blue Owl unit developing the 1,400-acre Project Jupiter campus in Doña Ana County, citing delays in securing power. It would let the company defer payments should the site miss its 2028 target. The campus is part of Oracle’s agreement to supply capacity to OpenAI and of Stargate. A natural gas pipeline meant to start service in mid-August and fuel the site was pushed back nearly six months to February 1, 2027. Oracle shares fell on the news.

Sources

  1. Bloomberg, “Oracle Cites ‘Force Majeure’ to Shield Itself on Controversial Data Center”, (bloomberg.com)
  2. Reuters (BNN Bloomberg), “Oracle triggers ‘force majeure’ on data centre project over power delays, source says”, (bnnbloomberg.ca)
  3. Source NM, “Proposed gas pipeline for Project Jupiter data center delayed to 2027, filings show”, (sourcenm.com)

Corrections and updates

  1. The version first posted on Instagram said the gas pipeline was due to start service “this month.” According to Source NM, citing FERC filings, the original in-service date was August 15, 2026; the text has been corrected.

About this story

This story was posted on Instagram by @jarrus.tech on Sept. 27, 2026.